A. No person may begin construction of any community water system, community sewer system, or drainage facilities until the developer has complied with WMC Chapters 13.04, 13.08 and 13.12. No person may begin construction of any improvement until they have:

1. Submitted to the engineer a detailed method of construction, which may include engineered plan and profile drawings at the option of the engineer, cost, and time schedule of all public improvements within the development;

2. Submitted to the engineer required approvals from all other governmental agencies; and

3. Received written approval from the engineer to proceed with construction and has paid the required inspection fees.

B. After the improvements are constructed, evidence of construction and approved as-built drawings must be submitted to the engineer by the developer’s engineer.

C. Improvements must be conveyed to the city by bill of sale or deed. (Prior code § 16.43.814)